21 Ajay can do a piece of work in 25 days and Sanjay can finish it in 20 days. They work together for 5 days and then Ajay goes away. In how many days will Sanjay finish the remaining work?
22 45 people take 18 days to dig a pond. If the pond would have to be dug in 15 days, then the number of people to be employed will be
23 2 men and 3 women can complete a work in 10 days, while 4 men can complete it in 10 days. In how many days will 3 men and 3 women complete the work?
24 A group of boys can do a certain piece of work in 40 days. If the group had 10 more boys, the work could be done in 5 days less. How many boys are there in the group?
25 A is 30% more efficient than B. How much time will they, working together, take to complete a job which A alone could have done in 23 days?
26 A can do a piece of work in 10 days, while B can do it in 6 days. B worked at it for 4 days. How long will A take to finish the remaining work?
27 Ten men can do a piece of work in 12 days. How many men are needed to complete the work in 20 days?
28 11 Sekh can do a work in 15 days and Vimal is 50% more expert than Sekh to complete the same work, then find total time taken to complete the work by Vimal: